The pictures below are from a recent project at a Sheffield Crematorium where we made modifications to the existing 150mm gas pipework to accommodate a new flue system which was being installed. The job entailed purging the existing gas pipe work with nitrogen before the gas pipe could be cut and new flanges welded on. New pipework was then installed and re-routed to supply the Cremators. The new pipeork was then re purged with gas.